  1. On 15 January 2015, the Home Building Amendment Act 2014 changed the terminology and definitions from structural to “major” and from minor to “in any other case” i.e. non-major. These amendments apply retrospectively to residential building work commenced or completed prior to the commencement of the amendment except in relation to a dispute in which proceedings had already commenced prior to the operation of the amendment or in relation to contracts entered prior to 1 February 2012.
  1. Two recent NSW Civil and Administrative Tribunal Appeal Panel decisions have considered the definition of major defect and how to establish whether a defect meets this definition, providing useful guidance on this topic.
GET NOTIFIED WHEN WE PUBLISH NEW Q&As, NEWS AND ARTICLES TO THE SITE
  1. The definition of a major defect is substantially different from the old definition of a structural defect.
  1. A major defect is defined as a defect in a “major element” of a building. This involves defects to the following parts of the building that are defined as a major element:
  1. In addition to affecting a “major element” of the building, a “major defect” must have the following consequences1 (emphasis added):
    1. The inability to inhabit or use the building (or part of the building) for its intended purpose; or
    2. The destruction of the building or part of the building; or
    3. A threat of collapse of the building or part of the building.
  1. A defect may also be a major defect if:
    1. It is a defect of a kind that is prescribed by the regulations as a major defect;2 or
    2. If it involves the use of a building product within the meaning of the Building Products (Safety) Act 2017) in contravention of that Act.3
  1. What defects are included in categories of major defects will depend upon the meaning of the words “destruction”, “the inability to inhabit or use the building”, or “threat of collapse”.
  1. It is possible that “major defect” will be considered to only include defects that have significant consequences. If so then the limitation period will be reduced to two years for some defects that previously would have had a six-year warranty because they will be regarded as non-major.
  1. Whilst there is very little judicial consideration of the meaning of major defect by the Courts in NSW, the definition has been considered recently in two cases this year by the Appeal Panel of the NSW Civil and Administrative Tribunal in relation to the question of jurisdiction. In other words, if a defect is not a major defect and more than two years have passed since completion of the building, then the claim is out of time and the Tribunal does not have jurisdiction.
  1. In Vella v Mir [2019] NSWCATAP 28 the Appeal Panel set out the sequence of analysis to decide whether a claim for a major defect was made within time as follows4:
    1. when the statutory warranty period starts;
    2. whether s.18E(2) applies if the statutory warranty has already been enforced;
    3. whether each of the defects is a major element in a building;
    4. whether each of the defects in a major element is a major defect;
    5. whether the application has been made within time by reference to the statutory warranty period.
  1. In Ashton v Stevenson [2019] NSWCATAP the Appeal Panel applied the decision of Vella and also found that the following must be established for a defect to be a major defect5:
    1. The first step in the analysis is that the defect must be part of a “major element” of a building.
    2. Inclusion in the definition of major element does not mean that the defect will be a “major defect”.
    3. The extent to which a defect impacts on the habitability or the integrity of the building needs to be proved by the party alleging a major defect (referring to Panchal v Jones t/as Oz Style Homes [2018] NSWCATD 238).6
    4. The consequences of the defect must be shown to have, or probably have, a proven consequence for the habitation, or use, of the building or to the integrity of the building.
    5. Section 18E(4)(a)(i) requires that there must be a proven, or probable, inability to inhabit or use the building.
    6. Section 18E(4)(a)(ii) and (iii) are at the more serious end of consequences or impact on a building. The reference to destruction does not mean minor process of deterioration, but evidence of a real possibility of destruction, not merely incidental damage or superficial deterioration.
    7. These are matters for evidence as to the actual impact which must involve more than a speculative or pessimistic assessment of possibilities in order to prove that the defect will have, or probably have, the prescribed consequences.
    8. The evidence must establish that the consequences are imminent or probable.
    9. Whilst expert evidence may assist in this analysis, such evidence is not determinative of the issue and must rise above speculation and suggestions as to possibilities.
    10. Evidence from the occupants of users of the building (as opposed to expert evidence) would be necessary to establish the claim.
  1. In summary, a “major defect” will have to overcome the criteria that the defect renders a building (or part of it) uninhabitable or incapable of use, destroys the building (or part of it) or imposes a threat of collapse of the building (or part of it). These criteria all involve a significant degree of seriousness.
  1. Additionally, establishing whether a defect is expert evidence or not is not simply a matter for expert opinion and will require evidence from occupants of the building to establish the seriousness of the defect, particularly in relation to the ability to use the building or a part of it for its intended purpose.
  1. Unless a defect can be proven to be a major defect, an owners corporation will be out of time to claim for some very significant and costly defects if proceedings are commenced outside of the 2- year limitation period for minor defects. It is important to take steps to review the building for defects after the first 12 months from the date of issue of an occupation certificate and obtain legal advice on pursuing the builder and developer.

Have a question or something to add to the article? Leave a comment below.

Embed Footnotes:
  1. Section 18E(4) of the HBA.
  2. Currently only “external cladding” is prescribed by the Regulations; clause 69A, introduced by the Home Building Amendment (Cladding) Regulation 2018, which commenced on 20 April 2018.
  3. Other than in respect of aluminium composite panel “external cladding”, no other building product use ban has been notified by the Secretary for Fair Trading under the Building Products (Safety) Act 2017.
  4. Vella v Mir [2019] NSWCATAP 28 at [44] decided on 31 January 2019.
  5. Ashton v Stephenson [2019] NSWCATAP 67 at [69] to [77].
  6. In Panchal v Jones t/as Oz Style Homes [2018] NSWCATD 238 at [87], the Appeal Panel found that “The defect does not need to be shown to make the habitation of use of the building (or part of it) impossible, but it must be such that the habitation or use of the building (or any part of it) cannot be for its intended purpose.
Read next: Helen Amanatiadis JS Mueller & Co Lawyers E. helenamanatiadis@muellers.com.au W. http://muellers.com.au/ P: 02 9562 1266 This post appears in Strata News #268. This article has been republished with permission from the author and first appeared on the JS Mueller & Co Website. Disclaimer: The information contained in this article is provided for your personal information only. It is not meant to be legal or professional advice nor should it be used as a substitute for such advice. You should seek legal advice for your specific circumstances before relying on any information herein. Contact JS Mueller & Co for any required legal assistance. Visit our Strata Building Defects OR NSW Strata Legislation After a free PDF of this article? Log into your existing LookUpStrata Account to download the printable file. Not a member? Simple – join for free on our Registration page.